Eskom has made significant progress in reducing load shedding, cutting outages from 84 days to just 17 days in the first eight months of 2025, Eskom Chairman Mteto Nyati said on Tuesday.
Nyati spoke during the PSG Think Big webinar, highlighting the utility’s ongoing turnaround efforts. Nyati, who was appointed chairman in 2022 alongside a new board, credited the improvements to a carefully planned and executed recovery strategy.
“We’ve done a lot of changes – we supported new management and came up with a two-year generation recovery plan which was approved by the board in March 2025,” he said.
“By March 2025, we wanted to be at the energy availability factor of 70%. Today, we are exactly at that. In fact, on many days, we’ve been above 70%.”